Refinery turnaround brought back on schedule
Challenge
A major unit turnaround was tracking days behind by the first week, with no integrated view of progress across disciplines.
Approach
Our remote desk rebuilt the integrated schedule, introduced daily progress curves and ran what-if recovery scenarios with the site team each morning.
Results